The rule is about readiness.
IAS 16 paragraph 55 starts depreciation when an asset is available for use, meaning it is where it needs to be and in the condition to operate as management intends. Paragraph 20 uses the same point to stop adding cost to the asset. Testing whether the asset works is part of its cost (paragraph 17); training staff, opening the new site and early operating losses are not (paragraphs 19 and 20).
For US tax, IRS Publication 946 uses a very similar test: property is placed in service when it is ready and available for a specific use, even if you have not started using it. Most US companies use the same ready-for-use date in their books, and an auditor will want a documented reason if yours differs.
One warehouse fit-out, start to finish.
Here is an example project. Operations signed off the line on 12 August after the commissioning tests, and it has run every shift since, if below full volume at first.
The example project
A warehouse fit-out: racking and a conveyor line.
One company, US dollars. Ready for use on 12 August 2026.
Before 12 August, posted as the bills came in
Mar engineering and design fees 40,000
Apr-Jun racking, supplied and installed 300,000
Jun conveyor equipment 420,000
Jul installation and commissioning tests 60,000
-------
820,000
Work done before 12 August, billed later
Oct contractor's final invoice (July work) 50,000
Feb 27 racking retention, 10%, released 30,000
After 12 August
Sep staff training on the new line 18,000
Sep-Dec slow first months while volume builds
Capitalized cost: 900,000. Life 10 years, straight line,
no residual value, 7,500 a month from the start month.The final invoice and the retention arrive after 12 August, but both pay for work finished before it, so both belong in the asset’s cost. The training belongs to September’s expenses. The slow first months are not costs to capitalize at all, just the line running below capacity.
Four start dates, four different years.
| Depreciation starts | Asset cost | 2026 depreciation | CIP at 31 Dec 2026 | Effect |
|---|---|---|---|---|
| Ready for use, August | 900,000 | 37,500 | 0 | Right |
| When the final invoice arrives, October | 900,000 | 22,500 | 0 | 15,000 too little depreciation |
| When the retention is paid, February 2027 | none yet | 0 | 900,000 | A working warehouse still in CIP |
| August, with training capitalized too | 918,000 | 38,250 | 0 | 2026 profit 17,250 too high |
Waiting for the final invoice is the most common slip, because the project “feels” open until the contractor bills. It costs two months of depreciation here. Waiting for the retention is worse: the warehouse has been running for four and a half months and sits in construction in progress at year end, which is the first thing an auditor looks for in a CIP balance. Capitalizing the training looks small, but it moves an 18,000 expense into the asset and spreads it over ten years.
Current answers, such as AccountingCoach, say there is no depreciation until the project is completed and placed in service. That is true, but “completed” is exactly the word teams read as the last invoice or the retention. Readiness is the test, and in this example it is two to six months earlier than the paperwork.
Accrue first, then capitalize.
The clean way through is to close the project in the month it becomes ready, not the month it is fully billed:
- Get a ready-for-use date signed by whoever runs the asset, with the evidence: the commissioning sign-off, the first production run, the occupancy certificate.
- Accrue the work done but not yet billed, here the 50,000 final invoice, into the project, and record the 30,000 retention as a liability when the work it holds back is done, not when it is paid.
- Capitalize the full 900,000 on the ready-for-use date and start depreciation that month.
- When the real invoice arrives, it clears the accrual. Any difference adjusts the asset’s cost and is depreciated over the remaining life.
- At each month end, review every CIP project with no new cost for 60 days. A quiet project is usually a finished one.
Guides for specific systems, such as this NetSuite one from Houseblend, cover the sign-off gate and the reconciliation well. What they do not show is what the choice of date does to the year’s numbers, which is what the table above is for.
Running capital projects in Rivane today.
Rivane has a Capital Projects (CIP) screen that collects costs against a project and then capitalizes the balance into a fixed asset on the placed in service date you enter.
Capital projects in Rivane, as built
# Capital projects (CIP) in Rivane, as built.
project number, name, and the CIP (WIP) GL account its
costs collect in; costs are in the company's
functional currency
cost each one is a bill, labour, material, expense
or other line with a date and an amount, and
posts its own journal entry: debit CIP, credit
the account you choose (AP, cash, wages payable)
locked a cost or capitalization dated in a locked
period is refused
capitalize placed in service date, asset name, method,
useful life in months, residual value; the
whole CIP balance moves into one new fixed
asset: debit the asset account, credit CIP
start depreciation runs from the in service month,
a full month by default
guard an in service date before the project's last
cost date is refused
after a capitalized project takes no more costsSome limits, as of today. Because an in service date before the last cost date is refused, date the accrual for late billed work on or before the ready-for-use date, or Rivane will not let you use it. A project capitalizes into one asset, so racking and a conveyor with different lives need two projects. Once capitalized, a project takes no more costs, which is another reason to accrue first. Rivane does not judge which costs qualify, so leaving training out is your call, and the CIP flow does not calculate capitalized interest.
The short version.
Start depreciating on the day the asset is ready for use. Accrue every cost for work done before that day, capitalize on that date, and expense what follows. In the example, that is 37,500 of 2026 depreciation on a 900,000 asset, and an empty CIP account at year end.
To see how Rivane runs the asset register, read Rivane fixed assets.
Frequently asked questions.
Can part of a project start depreciating before the rest is finished?
Yes. The test applies to each asset. If the racking is in use in June while the conveyor is still being installed, the racking is available for use in June and starts then. Keep the two as separate items so each gets its own start date and its own life.
Does the asset have to be in full use before depreciation starts?
No. IAS 16 starts depreciation when the asset is available for use, and IRS Publication 946 treats property as in service when it is ready and available, even if it is not yet used. Running below capacity while volume builds does not move the date.
Is the tax placed in service date always the same as the book date?
The tests are close, both turning on when the asset is ready for its intended use, so the dates usually match. The methods and conventions that follow differ, so keep the date once on the asset and let each book apply its own rules from it.
Sources
- IAS 16 Property, Plant and Equipment, as adopted in Commission Regulation (EU) 2023/1803. Paragraphs 16 and 17 (what goes into cost, including testing), 19 and 20 (what does not, and when adding cost stops) and 55 (depreciation begins when the asset is available for use).
- IRS, Publication 946 (2025), How To Depreciate Property. “Placed in Service”: property is in service when it is ready and available for a specific use, with three examples.
- AccountingCoach, How do you account for a project under construction? Read as a current answer.
- Houseblend, NetSuite construction in progress: capitalize and reconcile (10 November 2026). Read as a current answer.
A note on how this was researched. IAS 16 was read from the EU Official Journal text of Regulation 2023/1803 and Publication 946 from the IRS file, not from summaries. The two guides were read as current answers. The project and every amount are examples. The Rivane section describes the product as built today, checked against the capital projects code rather than marketing copy. This is not accounting advice for your specific case.
On embedded social posts: we looked for public posts from standard setters or practitioners on when construction in progress starts depreciating and found none we could verify as current and relevant, so this article uses ordinary citations instead.